Finland Review

image

Illustration of the future tram. Photo: WSP Finland Oy / City of Vantaa

Construction of the Vantaa tram has begun

Construction work will affect train traffic through Tikkurila from June to December.

Preparatory work for the Vantaa tram began after midnight on Monday at Tikkurila station.

Destia’s project manager Pekka Kivelä says that the work will create the conditions for the project to stay on schedule.

Construction work will affect train traffic in Tikkurila from June to December 2025.

The Vantaa tram is scheduled to be completed in 2029 and run from Mellunmäki in Helsinki to Helsinki-Vantaa Airport.

Preparatory work for the Vantaa tram began after midnight on Monday at Tikkurila station.

Destia’s project manager Pekka Kivelä, who is responsible for the western section of the Vantaa tram project, says that work has started well.

“The preparatory work will create the conditions so that when the project starts in the autumn, we have the prerequisites to stay on schedule.”

At this stage, rail bridges will be built for long-distance and commuter trains so that the tram construction site does not interfere with train traffic.

Construction work will affect the departure tracks of trains at Tikkurila station. First, tracks 5 and 6 will be out of service for a couple of weeks.

The track closures will be implemented in four stages, and later other tracks will also be temporarily out of service.

The works will affect train traffic passing through Tikkurila from June to December 2025. K, I and P trains will run less frequently for five weeks in the summer between 23 June and 27 July.

After the construction of the railway bridges, the construction of the actual tram tunnel will begin in the autumn.

The construction of the tunnel to Tikkurila station will take three years.

Some of the construction work causes noise and noisy work is sometimes carried out at night.

Works that cause noise include, for example, the installation of sheet pile walls and bored pile driving.

“A large part of the time is work that is interpreted as noisy work,” Kivelä says.

The Vantaa tram project has been discussed several times in the city council.

Last May, an extraordinary city council meeting was held on the topic of the tram, where supporters of the tram once again defeated opponents of the tram. The opponents would have liked to postpone the project until a more financially favorable time.

The alliance model has been chosen as the implementation model for the Vantaa tramway.

In the project plan approved two years ago, the total costs of 606 million euros would be divided so that Vantaa’s share would be 414 million euros. The state is participating in the project with 30 percent. The final price tag for the project should be known after the summer.

The Vantaa tram is scheduled to be completed in 2029. The tram runs from Mellunmäki in Helsinki to Helsinki-Vantaa Airport.

Related Posts

Vantaa decided to lease a plot of land for the Kivistö event arena

The arena project passed a milestone in Vantaa. The city leases land in Kivistö to the hall company.Vantaa has received additional clarifications reg...

The international financier of the giant Kivistö arena still remains a secret

The Vantaa City Board will convene an extraordinary meeting on Thursday, as insufficient information was received about international funding last wee...

Lähijunaliikenteessä myöhästymisiä henkilövahingon vuoksi

Lentokentälle kulkevat I- ja P-junat kulkevat myöhässä tai ne on peruttu.Vantaan Kivistössä on tapahtunut henkilövahinko tiistaina illalla kell...

New age pop band Komiat has reached new generations on Tiktok

The Komiat orchestra, which is gaining popularity on Tiktok, played three sold-out nights at the Backas restaurant in Vantaa during Midsummer week.You...